<p>This study examines the intricate task of predicting construction duration for drill-and-blast tunnels utilizing machine learning (ML) techniques. First, a comprehensive dataset (500 data points) encompassing 20 diverse parameters was compiled by constructing eight tunnels. After meticulous analysis, 17 of the 20 parameters were identified as crucial for training the algorithms. The overbreak and tunnel cross-section parameters were found to exert a significant influence on the tunnel construction duration. To enhance the predictive accuracy of the ML models, an intensive hyperparameter tuning process was conducted. The findings underscored the effectiveness of the Gaussian process regression model in capturing complex and nonlinear relationships, achieving an average R-squared of 0.89. Additionally, an ML-based graphical user interface (GUI) was developed to facilitate real‒time estimation of tunnel construction duration. This GUI not only enables initial predictions but also allows for dynamic updates throughout the construction phase, enhancing its practical utility.</p>

错误:搜索内容不能为空,请输入英文关键词
错误:关键词超出字数限制,请精简
高级检索

Machine learning approaches for predicting the construction time of drill-and-blast tunnels

  • Arsalan Mahmoodzadeh,
  • Hamid Reza Nejati,
  • Nejib Ghazouani,
  • Abdulaziz Alghamdi

摘要

This study examines the intricate task of predicting construction duration for drill-and-blast tunnels utilizing machine learning (ML) techniques. First, a comprehensive dataset (500 data points) encompassing 20 diverse parameters was compiled by constructing eight tunnels. After meticulous analysis, 17 of the 20 parameters were identified as crucial for training the algorithms. The overbreak and tunnel cross-section parameters were found to exert a significant influence on the tunnel construction duration. To enhance the predictive accuracy of the ML models, an intensive hyperparameter tuning process was conducted. The findings underscored the effectiveness of the Gaussian process regression model in capturing complex and nonlinear relationships, achieving an average R-squared of 0.89. Additionally, an ML-based graphical user interface (GUI) was developed to facilitate real‒time estimation of tunnel construction duration. This GUI not only enables initial predictions but also allows for dynamic updates throughout the construction phase, enhancing its practical utility.