Generation schemes for the resource-constrained project scheduling problem with partially renewable resources and generalized precedence constraints
摘要
In recent years, new resource types have been established in project scheduling. These include so-called partially renewable resources, whose total capacity applies only to a subset of periods in the planning horizon. In this paper, we consider the extension of the resource-constrained project scheduling problem with those partially renewable resources as well as generalized precedence constraints with the objective of minimizing the project duration (RCPSP/max-